Construction Projects

BC 2019 const

  under const    Construction Projects Map
         cone        Construction in Bay County

Trumbull Street Reconstruction

  • Center Ave. to Woodside Ave.

  • Construction Dates: 

    • Phase 1:  Complete

    • Phase 2:  April 15 - Nov. 1, 2019

  • Construction Low Bid:  $2,689,707

  • Traffic Maintenance:  Detoured on Johnson and Madison

Trumbull Street Map

Phase 2 (April - October 2019) will consist of the remaining removal items and construction work.  Traffic will be detoured during this phase.

Trumbull Street will be reconstructed between Center and Woodside. Work includes new storm sewer, asphalt pavement, sidewalks, and watermain, and curb and gutter.  

The street will be widened slightly to allow for three lanes - one in each direction with a center left turn lane.  The center left turn lane will reduce rear-end and side-swipe accidents, as well as allow the through traffic travel at a consistent pace, reducing air pollution.  The narrower through lanes will encourage motorists to drive at a steady, calm pace.  

The road and drainage portions of this project are being funded up to 70% through MDOT Local Agency Programs.  Watermain costs are reduced by coordinating with this project.

First Street Reconstruction

  • First Street is OPEN
  • Seeding and additional signing and striping will occur in the spring of 2019.

    First Street was reconstructed between Washington and Madison. Work included new separated sanitary and storm sewers, asphalt pavement, sidewalks, and minor watermain work.  Prior to the project, the combined sewer was failing and causing pavement issues. Tri-City Groundbreakers is the contractor.

Sidewalk Replacement Program

The sidewalk program is on hold during the winter.  Work will resume in the Handy Middle School neighborhood in the spring.  Affordable Contracting is the Contractor.

Sidewalk Maps:
Handy Neighborhood Sidewalk

  1. Rachel Phillips, P.E.

    Municipal Engineering Manager

MDOTVets Bridge Rehabilitation

MDOT will be upgrading and repairing the mechanical systems and deck concrete on Vets Bridge Jan 2 - Aug 2, 2019.
 
  • Jan 7 - Apr 14:  Periodic Single Lane Closures
  • Feb - March: Occasional Nighttime Detours
  • Apr 16 - Jun 14:  Detours (one bound at a time)
  • June 15 - Aug 2:  Periodic Single Lane Closures
Anlaan Corporation is the contractor, with the low bid of $2,717,484.33.  Traffic will be detoured April 16th - June 14.


Jenny St. (M-25 WB) / Henry St. Intersection Safety Upgrades

MDOT will be installing High Friction Surface Treatment and concrete patching on westbound M-25 (Jenny and 7th Streets) Aug 12 - Sep 27, 2019.  Vets Bridge traffic (Catherine to Water Streets) will be detoured on Lafayette Bridge, and Henry traffic will be detoured on Midland and Wilder, Aug 12 - 27.


M-13 (River Road/Broadway) Rehabilitation

MDOT will be rehabilitating the pavement with a 2-course (3-1/2 inches) between the interchange of I-75 and McGraw Street in 2019.  There will be lane closures throughout the project.

Stay tuned for Upcoming Projects!

  • Johnson Street - Woodside to Water:  This project will reconstruction the asphalt roadway, replace sanitary and storm sewers, replace watermain, replace/add sidewalks, and replace/add curb and gutter.  The design, designed by ROWE, is 80% complete.  Construction is tentatively scheduled for March - October, 2020.
  • Lafayette Bridge Replacement:  MDOT will be replacing the Lafayette Bascule Bridge (bridge on the east side of the Middlegrounds) in 2020-2022.  For preliminary information, click here.  Final plans are being developed.

Construction Quick Links

Site Tools