Construction Projects

2019 Construction Rev

Trumbull Street Reconstructiontrumbull2

- Center Ave. to Woodside Ave.

- Construction Dates:  April 1 - November 1, 2019

- Construction Low Bid:  $2,689,707

- Traffic Maintenance:  Detoured on Johnson and Madison

June Work Plan:  Crews will be working on Storm Sewer and Watermain

Trumbull Street is being reconstructed between Center and Woodside. Work includes new storm sewer, asphalt pavement, sidewalks, and watermain, and curb and gutter.  

The street will be widened slightly to allow for three lanes - one in each direction with a center left turn lane. The narrower through lanes will encourage motorists to drive at a steady, calm pace, reducing air pollution.  The sidewalks will remain in the same location.

Adding the dedicated left turn lane is expected to significantly decrease accidents.  In the past 10 years, 54% of the accidents in this section could have been avoided with a center left turn lane.  This includes 70 personal injuries that could have been avoided!

The road and drainage portions of this project are being funded up to 70% through MDOT Local Agency Programs.  Watermain costs are reduced by coordinating with this project.  Tri-City Groundbreakers is the Contractor, and OHM Advisors is performing the Construction Administration.
Trumbull Street Map
For more information, see Trumbull Information Presentation

Sidewalk Replacement Program

sidewalk repaired

On March 18, the City Commission voted to move to a Ward-Based location map.  Poor sidewalk will be replaced, beginning in the northeast quadrant of the 6th Ward.  As funding becomes available, the program will move Ward to Ward.  10% of the funds will be available for emergency repairs throughout the City.  Those requests will go through the Request Tracker on the City's Website.  Affordable Contracting is the Contractor.

First Street Reconstruction

  • Final work and repairs will be complete in June.

    First Street was reconstructed between Washington and Madison. Work included new separated sanitary and storm sewers, asphalt pavement, sidewalks, and minor watermain work.  Prior to the project, the combined sewer was failing and causing pavement issues. Tri-City Groundbreakers is the contractor.

MDOTVets Bridge Rehabilitation

MDOT will be upgrading and repairing the mechanical systems and deck concrete on Vets Bridge Jan 2 - Aug 2, 2019.
 
  • Jun 15 - Aug 2:  Periodic Single Lane Closures
Anlaan Corporation is the contractor, with the low bid of $2,717,484.33.  

Jenny St. (M-25 WB) / Henry St. Intersection Safety Upgrades

MDOT will be installing High Friction Surface Treatment and concrete patching on westbound M-25 (Jenny and 7th Streets) Aug 12 - Sep 27, 2019.  Vets Bridge traffic (Catherine to Water Streets) will be detoured on Lafayette Bridge, and Henry traffic will be detoured on Midland and Wilder.

M-13 (River Road/Broadway) Rehabilitation

MDOT is rehabilitating the pavement with a 2-course (3-1/2 inches) between the interchange of I-75 and McGraw Street.  Significant completion is scheduled for October 18.    There will be lane closures with flagging operations throughout the project.

Lafayette Bridge Replacement

MDOT will be replacing the Lafayette Bascule Bridge (bridge on the east side of the Middle Grounds) in 2020 - 2022.  Final plans are being developed, and the timeline may vary.

Stay tuned for Upcoming Projects!

  •  Wenona Avenue - Ionia to N. Union:  This project will reconstruct the asphalt roadway, replace storm sewer and watermain, and replace sidewalks and curb/gutter.  It will also improve geometrics at some intersections to improve safety.  The whole project is estimated to cost $8 million and will be constructed over 3 years:  2021, 2022, 2023.  The City will receive $3.4 million from Act 51 MDOT Federal Funds.

Construction Quick Links

  1. Rachel Phillips, P.E.

    Municipal Engineering Manager

Site Tools